April, 1995
Arizona Water Resources,
Joe Gelt
ed.,
vol.
4,
no.
4,
12
pp.,
Water Resources Research Center,
April, 1995
The City of Tucson has narrowed its options for using its Central Arizona Project water allocation to four: direct treatment and delivery through the existing treatment plant after replacing deteriorating mains; augmenting treatment with a filtration stage to remove salts; blending CAP water with equal amounts of groundwater; and recharging CAP water using spreading basins, streambeds, and/or injection wells.